Power behind the throne
from: Offshore Engineer
by: Darius Snieckus Thursday, July 12, 2007
Fruition for a contract first signed by Aker Kvaerner and BP in October 2005 to supply game-changing subsea boosting stations for the operator’s enhanced oil recovery project on the US Gulf King field. Darius Snieckus reports.
Atrio of Aker Kvaerner subsea MultiBooster pumps arrives in the US Gulf this month ready to be installed as part of plans by BP to boost production from its deepwater King development. Though the operator says only that the pumps will increase output ‘significantly’ from the field, located in water depths of more than 1700m on Mississippi Canyon blocks 84, 85, 128, and 129, studies show boosting can increase oil recovery by 15-20% on subsea wells averaging production of 10-30 million barrels, that is around 2-6 million barrels/well, making the return on the NKr220 million pump contract one likely to be swiftly realized by BP. First flow from the retrofit installation is scheduled for late in the year.
‘This represents a key milestone for Aker Kvaerner’s processing and boosting technology,’ enthuses Aker Kvaerner Subsea senior vice president for trees/processing and boosting Jarl Kosberg. ‘The installation of these pumps will extend the production lifetime of the field and increase the ultimate oil recovery for the operator.’
This first subsea multiphase pump application in water depths greater than 1000m, being tied back 29km to the host Marlin platform, also enters the record books as the longest subsea pump tieback yet undertaken by the offshore industry. ‘We are extremely pleased to work with BP on this important project,’ continues Kosberg. ‘This technology – engineered and produced at Aker Kvaerner’s subsea facility in Tranby, Norway, is a major step forward for us.’
‘Subsea boosting can be applied either early or later in a project,’ notes Gunder Homstvedt, engineering manager of Aker Kvaerner Subsea Boosting. ‘By boosting pressure an operator can deliver added production from the outset of a project and help deplete a field quickly, reducing overall opex, or it can be applied later to defer initial capex and extend producing life. Either way it can be a winner.’
The potential of the MultiBooster pump has long been recognised. Trialled under a pilot project at the UK North Sea Lyell field (OE September 2006), the King delivery will move the technology toward its first full-scale commercial application.
The MultiBooster has a history which has its roots in the 1980s with the development of the Kvaerner Booster Station, which consisted of a separator, centrifugal pump and centrifugal compressor mounted vertically, that was designed to separate gas and liquids before pumping them as separate streams. After five years of testing it was concluded that while KBS would work on the seabed, it was ‘before its time’ in terms of the subsea market being ready for it, and, in 1994, was shelved.
Before the decade was out however, a multi-partner Demo 2000 programme led by Hydro was rethinking the technology as part of a programme to boost pressure from the operator’s Sognefjord development off Norway from 26bar to 65bar and commingling it with production from other fields (OE December 2002). The pump module was tested using water at what became Aker Kvaerner Subsea’s facility at Tranby, and later at Statoil’s K-Lab at KÃ¥rstø in simulated subsea conditions on a feed of natural gas and condensate, proving it could handle a variety of flow conditions and a gas void fraction of 98% – equivalent to ‘wet gas compressor conditions’.
Last month, three 57t MultiBoosters, two duty and one spare, were lifted aboard the Normand Cutter destined for King.Wells at the field are spaced in such as way as to call for two pump stations rather than one, but in all, three wells will be boosted. One MultiBooster will operate on the production from wells D5 and D3, the other on well D6. The single six-corepower umbilical from the Marlin TLP will run first to D5 and D3, using three of the cores, while the other three cores will continue to D6. The MultiBoosters built for King will each have a processing capacity of some 150,000b/d.
Aker Kvaerner’s total workscope for King encompasses delivery of subsea pumps outfitted with Bornemann twin screw technology, as well as engineering, procurement and construction of the station manifolds, variable speed drives, topside and subsea control systems, topside lube oil hydraulic power unit and high voltage connectors and jumpers.
The subsea MultiBooster is foreseen as a fit for projects involving boosting of low pressure wellstream from subsea tiebacks, as at King, tail-end production for increased oil recovery, and greenfield subsea developments. BP has subsea pumping in the frame for ‘consideration in future development plans in its global portfolio to improve recovery’.
Last year, Aker Kvaerner’s MultiBooster was selected for a Spotlight on New Technology Award at the Offshore Technology Conference in Houston. OE